MEP & Structural Engineering for Coastal Apartments, CA

MEP engineering and Title 24 compliance design for California coastal apartments

InnoDez completed this multi-family residential project by delivering specialized Apartment MEP and Structural Engineering solutions. Specifically, we provided structural engineering, MEP design, and Title 24 energy calculations.

Apartment MEP and Structural Engineering:

Case Study – Coast Street Apartments

Project Overview & Key Details

  • Project Name: Coast Street Apartments
  • Project Location: 13040 Coast Street, Garden Grove, CA 92844
  • Architect: BSB Design
  • Engineering Services Provided by InnoDez

Project Scale and Specifications

The Coast Street Apartments is a high-density, multi-family residential development. Our team engineered the project to optimize urban living space under California’s State Density Bonus Law. Key scale and architectural logistics include:

  • Total Building Volume: The development features a massive total gross building floor area of 61,297 square feet.
  • Structural Configuration: The 5-story building consists of 4 stories of Type V-A wood construction. Furthermore, this structure sits safely over a 1-story Type I concrete podium base for parking and lobby spaces.
  • Residential Units: The property offers 34 total multi-family units. These include 12 one-bedroom flats (Unit Type A, 666 SQ FT) and 22 two-bedroom flats (Unit Type B, 935 SQ FT).
  • Site Logistics: The project sits on a net lot area of 21,829 square feet. Additionally, the building footprint covers 11,904 square feet.
  • Parking Infrastructure: A ground-level garage offers 45 total parking stalls. Consequently, it features standard, tandem, EV-ready, EV-capable, and EV-equipped infrastructure.
Sustainable MEP engineering and HVAC design blueprint for modern coastal apartment complex.
Comprehensive building systems design for the Coast Street Apartment project, optimizing energy efficiency and coastal resilience.

Engineering Challenges & Structural Solutions

1. Structural Engineering Challenges & Code Compliance

The structural engineering team had to navigate complex site hazards, heavy load distributions, and evolving local building codes:

  • Foundation and Slab Design Requirements: Supporting four levels of wood construction over open parking required an elevated post-tensioned (PT) podium slab system. Therefore, the team evaluated shallow footings, mat foundations, and PT slab-on-grade systems to ensure optimal stability.
  • Geotechnical and Site Constraints:
  • Liquefaction and Groundwater: The building site presented shallow groundwater levels and high soil liquefaction potential. Combined with massive column loads, these conditions severely limited allowable soil bearing capacity.
  • Soil Improvement: To address these poor soil conditions safely, engineers leveraged ground improvements like Rammed Aggregate Pier (RAP) systems. As a result, this increased bearing capacity and limited heavy site grading.
  • Code Compliance Updates: During the project, the team transitioned design criteria from CBC 2022 / ASCE 7-16 to CBC 2025 / ASCE 7-22 codes. Consequently, this required extensive updates to geotechnical and structural engineering reports.
  • Design Coordination: The structural and architectural teams maintained continuous coordination. Thus, they aligned concrete shear walls, foundation lines, and slab systems without interrupting architectural flow.
  • Data Availability Obstacles: An official geotechnical report was missing at the start. However, the engineering team proceeded using baseline assumptions to keep the project moving forward.

2. MEP Engineering Challenges & Underground Coordination

  • Intricate Garage-Level MEP Coordination: A central challenge involved coordinating gravity drainage plumbing in the ground-floor garage. Gravity lines require precise sloping, creating conflicts with low-clearance structural beams. However, plumbing and structural teams integrated closely to route lines around structural nodes. Consequently, they maintained proper gravity flow and full vehicular headroom clearance.

The InnoDez Advantage: Integrated Apartment MEP and Structural Engineering

When developers outsource structural engineering, MEP design, and energy compliance to separate firms, communication gaps naturally arise. Consequently, these silos regularly result in spatial clashes, costly change orders, and prolonged plan check delays.

 

InnoDez managed Structural Engineering, MEP Engineering, and Title 24 Calculations under one unified umbrella. Thus, we delivered a streamlined asset for the Coast Street Apartments project:

  1. Real-Time Spatial Clash Resolution: Our team mitigated physical conflicts between garage plumbing lines and concrete beams instantly. Because our designers work in the same ecosystem, they engineered adjustments in real-time without delay.
  2. Synchronized Title 24 & Structural Frameworks: Energy code insulation values heavily impact framing and HVAC sizing. Therefore, InnoDez cross-referenced Title 24 calculations with architectural details from day one to ensure swift compliance.
  3. Agile Responses to Code Transitions: Moving parameters to CBC 2025/ASCE 7-22 guidelines required multi-system adaptations. Furthermore, our unified team ensured structural layout changes matched mechanical routing pathways seamlessly.
  4. Compressed Timelines & Mitigated Risk: Working ahead of a geotechnical report carries risk. However, our engineers operated in tandem to adjust structural assumptions dynamically. As a result, this protected the client from timeline delays.

Project Summary & Next Steps

InnoDez delivered end-to-end Apartment MEP and Structural Engineering solutions for the Coast Street Apartments in Garden Grove, CA. By uniting structural engineering, MEP design, and Title 24 calculations, we successfully resolved podium slab challenges. Additionally, our team mitigated soil liquefaction risks and streamlined city plan checks.

Learn more about our comprehensive Services or Contact Us to discuss your upcoming engineering project.